Brook House, Whitstable

John Wesley School,Ashford
03/03/2016


		

Project Overview

Full Refurbishment of KCC Social Services offices 100,000 sqft

Project Description

  • The works were carried out on a phased programme of 6months.
  • Working floor by floor as KCC moved staff throughout the building.
  • Working in conjunction with all other trades, we completed the project on time and to the satisfaction of the client.

Project Works Detail

  • Strip out of redundant electrical services.
  • The modification and extension of existing switchgear.
  • Installation of small power via under-floor track system for floor outlet boxes, desk power modules and general purpose power to serve the office areas.
  • Fit-out of the landlord core areas throughout the building.
  • Installation of LED lighting throughout.
  • External lighting.
  • Disabled alarm systems.
  • Testing and Commissioning